CLOVER LANE CONSTRUCTION UPDATE
The contractor is continuing to focus on completing the sidewalks, driveways and ADA-wheelchair ramps associated with the project. The roadway paving is now complete for the entire project, from Birchman Ave. to Camp Bowie Blvd. The road should be completely open for use, except for the area near Camp Bowie that is still undergoing pedestrian facilities improvements.
After completing the installation of the new storm sewer system in El Campo Ave. several months ago, the only task that remained on that street was to replace the pavement so that the street looks nice and new. The contract will begin working on that task this week.
The flatwork portion of the project (sidewalks, driveways, etc.) will last for a few more weeks. The new pavement on El Campo will be finished in by the end of November.
Here is a time line:
November 9-13: Finish up the majority of sidewalks and driveways remaining, repaving of El Campo Ave.
November 16-20: Project cleanup, installation of sod, concrete joint sealing, reinstallation of signs
November 23-27: Continue cleanup, reinstallation of historic bricks at Camp Bowie Blvd. intersection
The intersection of Camp Bowie Blvd. and Clover Lane will still experience temporary closures as pedestrian facilities are installed in and around the street. No other parts of Clover Lane should experience major closures.
As flatwork continues, there will be temporary closures of sidewalks and ramps which could cause pedestrians to seek alternative routes. El Campo Ave. between Belle Place and Clover Lane will have temporary closures once the street is being repaved. You will be notified in advance if access to your driveway is impeded.
No properties will experience water/sewer disruptions.
Greg Robbins
Senior Project Manager
TPW\Capital Delivery Division
817-392-2333